Roll Conveyor
-
Installation
1. Unpack and inspect: check all the parts as per packing list. In case of any defect, please contact the sales department of our company in a timely manner.
2. Correctly ascertain the center line according to the foundation drawing, and then fix the shaft line of equipment, correct corresponding position dimensions, cast equipment foundation with re-enforced concrete.
3. The foundation goes through a certain period of maintenance (general 15 days), correcting until no error, install the equipment. Installation procedure is as follows:
(1) Check and clean each foundation embedded plate
(2) Lift the bracket onto the foundation, matched well with other related equipment, adjust position
(3) Fasten the equipment feet by fixing device
4. After completing installation, then commissioning.
-
Operation Instruction
- When operating, feed raw material evenly as far as possible and control the material in allowed size
- Shut down or start is not advisable when the machine is fully loading
-
Maintenance
- Check the lubrication of equipment running parts usually, and inject the lubricant regularly
- Change new lubricating oil for reducer after running for 7-14 days and afterward change each 3-6 months accordingly.
- Regularly check the equipment, no loosing bolts, no exceeded rated current of motor; when temperature rise of the bearing exceed the ambient temperature 35 degree, shut down to check.
- According to the using situation, overhaul one time about half a year is advisable.
Grease Chart
Oiling point location Lubricant Lubricating interval Bearings ZG-3 calcium base grease Each month Sleeve roller chain ZG-3 calcium base grease Each 15 days Motor Maintain according to the manufacturer instruction -
Spare parts
- Bearing with seat UCFLU208 (with fastening screw, no eccentric sleeve)
- Chain 16A-34 short L=863.6mm